The Design Document page provides a description of the algorithms, implementation and planned testing including unit, verification, validation and performance testing. Please read Step 1.3 Performance Expectations that explains feature documentation requirements from the performance group point of view.
Design Document
In the table below 4.Equ means Equations and Algorithms, 5.Ver means Verification, 6.Perf - Performance, 7. Val - Validation, - competed, - in progress, - not done
Title: MPAS-CICE
Requirements and Design
ACME Ocean-Ice Group
Date: September 25, 2015
Summary
Requirements
Requirement: CICE 4.0 column physics
Date last modified:
Contributors: Adrian Turner
MPAS-CICE is required to utilize column physics that is equivalent or better than CICE 4.0.
Requirement: CICE 4.0 EVP solver
Date last modified:
Contributors: Adrian Turner
MPAS-CICE is required to use a constitutive relation that is equivalent or better than the elastic-viscous-plastic (EVP) solver used in CICE 4.0.
Requirement: CICE 4.0 velocity solver
Date last modified:
Contributors: Adrian Turner
MPAS-CICE is required to use a velocity solver that is equivalent or better than that used in CICE 4.0.
Requirement: CICE 4.0 transport
Date last modified:
Contributors: Adrian Turner
MPAS-CICE is required to use a transport scheme that is equivalent or better than that used in CICE 4.0.
Algorithmic Formulations
Design solution: CICE 4.0 column physics
Date last modified: September 25, 2015
Contributors: Adrian Turner and Elizabeth Hunke (Unlicensed)
For each
Design solution: CICE 4.0 EVP solver
Date last modified: September 25, 2015
Contributors: Adrian Turner
For each
Design solution: CICE 4.0 velocity solver
Date last modified: September 25, 2015
Contributors: Adrian Turner
For each
Design solution: CICE 4.0 transport
Date last modified: September 25, 2015
Contributors: William Lipscomb (Unlicensed)
For each
Design and Implementation
Implementation: CICE 4.0 column physics
Date last modified: September 25, 2015
Contributors: Adrian Turner and Elizabeth Hunke (Unlicensed)
For each
Implementation: CICE 4.0 EVP solver
Date last modified: September 25, 2015
Contributors: Adrian Turner
For each
Implementation: CICE 4.0 velocity solver
Date last modified: September 25, 2015
Contributors: Adrian Turner
For each
Implementation: CICE 4.0 transport
Date last modified: September 25, 2015
Contributors: William Lipscomb (Unlicensed)
For each
Planned Verification and Unit Testing
Verification and Unit Testing: short-desciption-of-testing-here
Date last modified:
Contributors: (add your name to this list if it does not appear)
How will XXX be tested? i.e. how will be we know when we have met requirement XXX. Will these unit tests be included in the ongoing going forward?
Planned Validation Testing
Validation Testing: short-desciption-of-testing-here
Date last modified:
Contributors: (add your name to this list if it does not appear)
How will XXX be tested? What observational or other dataset will be used? i.e. how will be we know when we have met requirement XXX. Will these unit tests be included in the ongoing going forward?
Planned Performance Testing
Performance Testing: short-desciption-of-testing-here
Date last modified:
Contributors: (add your name to this list if it does not appear)
How will XXX be tested? i.e. how will be we know when we have met requirement XXX. Will these unit tests be included in the ongoing going forward?