Page Properties
idfeature

Dependencies Table for this feature

1.Design DocA1 Ozone Hole: Design Document
2.OwnerPhilip Cameron-Smith
3.PR ReadyDecember
4.Blocked By#None
5.Affects #Vertical resolution;  MAM4.
6.Issued PR 
7.PR OwnerSusannah Burrows
8.Integrated 
9.Hash/Tag#406
Git Branchcameronsmith1/atm/Ozone-hole-Linoz-v2



HTML Comment

Labels to choose from for the 'Done ?' and 'Approved ?' columns

(tick) - competed, (warning) - in progress, (error) - not done/not started


Checklist for the Code Review Process for this feature

Action RequiredAssignee - Task OwnerLinkDone ?Done DateApproved?ApproverApproved DateNotes
Phase 1 - Component Level Development and Testing
Design DocumentPhilip Cameron-SmithA1 Ozone Hole: Design Document

(tick)

  


 

(tick)

Shaocheng Xie  
Verification and Unit TestsPhilip Cameron-SmithA1 Ozone Hole: Verification Phase 1(tick) 

(tick) 


Phil Rasch (pnl.gov)  
Performance AssessmentPhilip Cameron-Smith A1 Ozone Hole: Performance Phase 1(tick) (tick)Shaocheng Xie  
Validation TestsPhilip Cameron-Smith A1 Ozone Hole: Validation Phase 1(tick) (tick)Shaocheng Xie  
Issue Pull RequestPhilip Cameron-Smith#406(tick) (tick)Shaocheng Xie  
PR IntegratorSusannah Burrows- 
integrated date----
Phase 2 - Coupled System Integration and Testing
Phase 2 Process Doc(error)(error)  

Feature's Coupled Performance(error)(error)   


Feature's Coupled Validation(error)(error)   


Final Approval to part of ACME model 
(error)----


Note: the design document for phase II is: NA1: Atmospheric Chemistry and Radiation