The first DECK simulation is the piControl simulation which requires a minimum of 500 years. Other experiments will all be initialized by branching of from piControl at various stages. A possible scenario is provided in the figure below. Historical_H1, 1pctCO2, and abrupt-4xCO2 would start from year 101 of piControl, amip from year 1870 of historical_H1, historical_H2 from year 151 of piControl and all remaining historical members would be spaced 50 years apart (201, 251, 301).

...

Initialization and final tuning (description)

piControl (simulation page)

Initialization

Due to time constraints, piControl year 1 (0001-01-01) initial conditions are taken from a pre-existing simulation rather than starting a new spin-up from scratch. The initial conditions are 0331-01-01 of 20171228.beta3rc13_1850.ne30_oECv3_ICG.edison.

Provenance of initial conditions:

Image Removed

Final tuning

...

)

...

  • 20180129.DECKv1a_piControl.ne30_oEC.edison : identical tuning as in beta3rc13, but with a slightly updated version of the code base.
  • 20180129.DECKv1b_piControl.ne30_oEC.edison : same, except for a minor retuning of clubb_c14: 1.08 → 1.06. This is expected to only change net TOA fluxes by a few hundreds of a W/m2, but may help further reduce long-term drift (without hopefully changing its sign).

...


abrupt-4xCO2 (simulation page)

...

historical (simulation page)

Initialization

  • Ensemble member H1: 0101-01-01 of v1b piControl
  • Ensemble member H2: 0151-01-01 of v1b piControl
  • Ensemble member H3: 0201-01-01 of v1b piControl
  • Ensemble member H4: 0251-01-01 of v1b piControl
  • Ensemble member H5: 0301-01-01 of v1b piControl

...