Action RequiredAssignee - Task OwnerLinkDone ?Done DateApproved?ApproverApproved DateNotes
Phase 1 - Component Level Development and Testing
Design Document

B9 - MOSART-Reservoir Stratification Design Document

(error)(tick) 

July 05, 2020

(error)



Verification and Unit Tests

B9 - MOSART-Reservoir Stratification Verification Phase 1


(error)(tick)
July 05, 2020(error)


Performance Assessment

B9: MOSART-Reservoir Stratification Performance Assessment

(error)(tick)

July 05, 2020(error)


Validation Tests

B9: MOSART-Reservoir Stratification Validation

(error)

(tick)July 05, 2020(error)


Issue Pull RequestWondie Yigzaw (Unlicensed)3674(tick)(tick)(error)


PR IntegratorGautam Bisht-(tick)integrated date----
Phase 2 - Coupled System Integration and Testing
Phase 2 Process Doc(error)(error)

Feature's Coupled Performance(error)(error)


Feature's Coupled Validation(error)(error)


Final Approval to part of ACME model
(error)----

...