Action RequiredAssignee - Task OwnerLinkDone ?Done DateApproved?ApproverApproved DateNotes
Phase 1 - Component Level Development and Testing
Design Document

B2 Mosart Heat Design Document

(tick)


Sep. 3, 2019 

(error)(tick)

Katherine Calvin (Unlicensed) 
Verification and Unit Tests

B2 Mosart Heat Verification Phase 1


(tick)Aug. 15, 2019(error)


Performance Assessment

B2 Mosart Heat Performance Phase 1

(tick)Aug. 15, 2019(error)


Validation Tests

B2 Mosart Heat Validation Phase 1

(tick)
(error)


Issue Pull RequestHongyi Li#3033(tick)Aug., 15, 2019(error)


PR Integratorassigned integrator-
integrated date----
Phase 2 - Coupled System Integration and Testing
Phase 2 Process Doc(error)(error)

Feature's Coupled Performance(error)(error)


Feature's Coupled Validation(error)(error)


Final Approval to part of ACME model